The Measure G projects are coming soon to O'Donnell Heritage Park! The following are included in this upcoming series II:
- Addition of an accessible concrete walkway around the park.
- site furnishings and accessible park accessories.
Timeline:
- Current Progress (March 2026): Intent to award the contract to the lowest responsible bidder, Lister Construction, was approved by the Advisory Board on 3/19/25 (Action 4).
- February (2026): RFP for Landscape Contracting released.
- January (2026): O'Donnell Heritage Park Conceptual Design presented by MTW Group at the CRPD Advisory Board Meeting on 1/15/26 and approved.